By right: nothing · ADU not by right

1. What you can build

1 unit2 units3 units4+ unitsGroup living
Multifamily – stand alone———
HomeA1 ADU—
—
Multifamily as part of a mix-use development———
Home✓2 ✓3 ✓4 A5 ADU—
—

✓ By right   A Administrative review   H Public hearing   — Not allowed   HOME = the main building   n Only under condition n

2. Lot standards

StandardValueExceptions
Minimum units4 units TMC 19.10.010

3. Building standards

StandardValueExceptions
Front setback
  • 0 ft6 TMC 19.09.100E.1.b(1)
  • 20 ft7 TMC 19.09 Table 9-2
Side setback
  • 0 ft6 TMC 19.09.100E.1.b(1)
  • 5 ft7 TMC 19.09 Table 9-2 note 31
Total side setbacks
  • 0 ft6 TMC 19.09.100E.1.b(1)
  • 30% of shoreline frontage7 TMC 19.09 Table 9-2
Rear setback
  • 0 ft6 TMC 19.09.100E.1.b(1)
  • 10 ft8 TMC 19.09 Table 9-2
  • Critical Area Buffer Setback from edge of buffer. When no buffer is present, the Setback is measured from the rear property line.9 TMC 19.09 Table 9-2
Building separation
  • 80 ft10 TMC 19.09.100E.6.c
  • Not set11 TMC 19.09 Table 9-2
Maximum height
  • 100 ft12 TMC 19.09.100E.1
  • 100 ft13 TMC 19.09.100E.1
  • 180 ft14 TMC 19.09.100E.6.b
  • 90 ft15 TMC 19.09.100E.1
  • 130 ft16 TMC 19.09.100E.1
  • 100 ft17 TMC 19.09.100E.1
  • 65 ft18 TMC 19.09.100E.1
  • 100 ft7 TMC 19.09.100F.1
Minimum height
  • 50 ft19 TMC 19.09.100E.1
  • 50 ft13 TMC 19.09.100E.1
  • No limit14 TMC 19.09.100E.1 Table 9-1
  • 40 ft20 TMC 19.09.100E.1
  • Not set7 TMC 19.09.100F
Maximum lot coverage
  • From grade to 50 feet in height: 100 percent coverage of development site permitted; From 50 feet to 100 feet: 70 percent coverage of the at-grade area is available for development, inclusive of required modulations; Above 100 feet: 50 percent coverage of the at-grade area is available for development, inclusive of required modulations.21 TMC 19.09.100E.3.a-c
  • Not set7 TMC 19.09.100F
  • Not set22 TMC 19.09.100E.6
Minimum parking0 spaces per unit TMC 19.07.100B.1.b

4. ADU standards

Lot

No standards.

Building

No standards.

5. Dividing land

DivisionApprovalLotsDensityEach new lot
Short subdivision TMC 13.05.070H Table H; 13.04.090A A 2 to 9 TMC 13.05.070H Table H; TMC 13.01.040 —
Minimum lot size
Not set TMC 19.09 Table 9-2
Subdivision TMC 13.05.110B; 13.05.070H Table H H 10 or more TMC 13.01.040 —
Minimum lot size
Not set TMC 19.09 Table 9-2
Binding site plan TMC 13.05.070H Table H; 13.04.088BOnly for: Multifamily as part of a mix-use development, Multifamily – stand alone A
Minimum lots
Not set TMC 13.04.088
—
Minimum lot size
Not set TMC 13.04.088

✓ By right   A Administrative review   H Public hearing   — Not allowed

Conditions

  1. All of these are true:
    • The site is in an upland location (not over-water or in-water)
    • The site is upland on the west side of the Foss Waterway, or on the east side south of the East 11th Street right of way, and not east of East D Street
    • The use provides a significant public benefit with respect to the public access and restoration goals of the Shoreline Master Program
    • Any of these is true:
      • Navigability is severely limited at the proposed site
      • The site is within shoreline jurisdiction but physically separated from the shoreline by a separate property, public right-of-way, or existing use
  2. All of these are true:
    • The site is in an upland location (not over-water or in-water)
    • The site is upland on the west side of the Foss Waterway, or on the east side south of the East 11th Street right of way, and not east of East D Street
    • The use provides a significant public benefit with respect to the public access and restoration goals of the Shoreline Master Program
    • Any of these is true:
      • The use is part of a mixed-use proposal or facility that supports water-oriented uses
      • Navigability is severely limited at the proposed site
      • The site is within shoreline jurisdiction but physically separated from the shoreline by a separate property, public right-of-way, or existing use
    None of these is true:
    • The building is adjacent to Dock Street or the esplanade
  3. All of these are true:
    • The site is in an upland location (not over-water or in-water)
    • The site is upland on the west side of the Foss Waterway, or on the east side south of the East 11th Street right of way, and not east of East D Street
    • The building is adjacent to Dock Street or the esplanade
    • The building includes water-oriented uses directly accessible from Dock Street or the esplanade
    • The use provides a significant public benefit with respect to the public access and restoration goals of the Shoreline Master Program
    • Any of these is true:
      • The use is part of a mixed-use proposal or facility that supports water-oriented uses
      • Navigability is severely limited at the proposed site
      • The site is within shoreline jurisdiction but physically separated from the shoreline by a separate property, public right-of-way, or existing use
  4. All of these are true:
    • The site is in an upland location (not over-water or in-water)
    • The site is upland on the west side of the Foss Waterway, or on the east side south of the East 11th Street right of way, and not east of East D Street
    • The building is adjacent to Dock Street or the esplanade
    • At least 25 percent of the shoreline frontage is occupied by a water-oriented use
    • The use provides a significant public benefit with respect to the public access and restoration goals of the Shoreline Master Program
    • Any of these is true:
      • The use is part of a mixed-use proposal or facility that supports water-oriented uses
      • Navigability is severely limited at the proposed site
      • The site is within shoreline jurisdiction but physically separated from the shoreline by a separate property, public right-of-way, or existing use
    None of these is true:
    • The building includes water-oriented uses directly accessible from Dock Street or the esplanade
  5. All of these are true:
    • The site is in an upland location (not over-water or in-water)
    • The site is upland on the west side of the Foss Waterway, or on the east side south of the East 11th Street right of way, and not east of East D Street
    • The building is adjacent to Dock Street or the esplanade
    • The use provides a significant public benefit with respect to the public access and restoration goals of the Shoreline Master Program
    • Any of these is true:
      • The use is part of a mixed-use proposal or facility that supports water-oriented uses
      • Navigability is severely limited at the proposed site
      • The site is within shoreline jurisdiction but physically separated from the shoreline by a separate property, public right-of-way, or existing use
    None of these is true:
    • The building includes water-oriented uses directly accessible from Dock Street or the esplanade
    • At least 25 percent of the shoreline frontage is occupied by a water-oriented use
  6. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is not east_side
  7. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is east_side
  8. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is east_side
    None of these is true:
    • A critical area buffer is present on the site
  9. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is east_side
    • A critical area buffer is present on the site
  10. The project uses the S-8 Alternative 2 development option
  11. None of these is true:
    • The project uses the S-8 Alternative 2 development option
  12. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is north_end
  13. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is site11_to_site10
    None of these is true:
    • The project uses the S-8 Alternative 2 development option
  14. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is site11_to_site10
    • The project uses the S-8 Alternative 2 development option
  15. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is site10_to_11th
  16. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is 11th_to_15th
  17. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is 15th_to_18th
  18. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is 18th_to_south
  19. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is one of north_end, site10_to_11th, 11th_to_15th
  20. Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is one of 15th_to_18th, 18th_to_south
  21. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is not east_side
    None of these is true:
    • The project uses the S-8 Alternative 2 development option
  22. All of these are true:
    • Which S-8 Table 9-1 segment of the Thea Foss Waterway the site is in, or the east side is not east_side
    • The project uses the S-8 Alternative 2 development option